This article was funded by LebTown donors as part of our Civic Impact Reporting Project.

The Cornwall Borough Planning and Zoning Commission recommended that council conditionally approve the Knoll plan, a 46-townhome development accessible from Boyd Street, at its monthly meeting Monday.

The Planning and Zoning Commission (P&Z) also recommended approval of seven waivers and failed to make a recommendation on a road improvement waiver requested for Granite Street.

A vote to recommend approval of the Granite Street improvements ended in a tie, with Greg Roussey and Joe Lescisko in favor and Bruce Conrad and Ray Fratini opposed, with John Karinch abstaining (as he does for all actions associated with Steckbeck Engineering because of his son’s financial interest in the employee-owned firm).

Fratini said a decision on the waiver is in council’s hands, and Conrad urged Granite Street residents and the developer to reach a compromise before council meets Oct. 12.

An earlier version of the plan, which included 11 parallel parking spaces along the north side of Granite Street and eight pull-in spaces on the southeast side, elicited concerns from street residents who said there were not enough parking spaces for their vehicles.

Residents now park in a paved area across from their homes, which is slated for development as part of the project. The borough, Fratini previously explained, cannot prevent Cornwall Properties from developing this land.

A Google Maps street view of Granite Street. Residents’ homes open directly onto the pavement, with no sidewalk or curbing, and residents park by pulling in across the street.

Since then, developer Cornwall Properties has provided sketches of multiple alternate plans and held a workshop with neighbors to hear their preferences. The most recent version of the plan includes 18 angled spaces and eight pull-in spaces, and makes the road one-way. However, this design requires a waiver from the borough for street improvements as the street is 18 feet wide and the borough does not typically allow angled parking.

Several Granite Street residents voiced continued dissatisfaction with the plan. Resident Lauren Shank distributed a handout questioning whether crosshatching and curb stops match the character of Miners Village as a historic overlay district.

Curb stops were floated for parking on the north side of the street due to resident concerns about cars crashing into their homes while parking, as resident porches are directly along the side of the road. Though neighbors have requested curbing, Cornwall Properties representatives have said it would not be possible due to the height of the road being level with neighboring homes’ foundations.

The plan only includes a paving overlay to slightly above the road’s centerline, which drew concern from residents and several members of the commission who were under the impression the whole road would be overlaid. Cornwall Properties representative Mike Swank said the developer heard from neighbors that they were worried about damage to their homes if the whole road was overlaid.

Swank said Cornwall Properties is still willing to overlay the whole road, including milling off 1.5 inches and paving 1.5 inches on top, but only if Granite Street residents sign waivers for possible damage to their homes caused by the work. Multiple Granite Street residents said Monday they were not willing to sign this waiver, and Swank said the developer was firm on requiring a waiver before they agreed to the full overlay.

Granite Street resident Lauren Shank voices concern about the potential effect of the plan on neighbors and pushes against the borough granting waivers.
Granite Street homeowner Andre Dyer says he is not willing to waive his rights as a homeowner for the full road to be overlaid.

Chad Smith of Steckbeck Engineering, representing Cornwall Properties, said that if the improvements waiver is not granted, the developer will adjust the plan to meet borough requirements including road width, also decreasing parking spaces. The earlier version of the plan with 19 spaces total met borough parking requirements.

Borough alternate engineer Josh Weaber said this adjustment would not require plan resubmission; if the waiver is denied, meeting road improvement requirements on Granite Street would be added as a condition to approval.

The seven other waivers requested by the developer, all recommended for approval with Karinch abstaining, are as follows:

  • SWMO 11A-308.4: Basin fencing requirement, with max basin depth of 3.8 feet and a 3:1 slope, due to maintenance problems, aesthetic concerns, and possible safety concerns for children who climb fencing and have trouble getting out.
  • SWMO 11A-309.2.B: 18-inch pipe diameter requirement, with the developer planning 15-inch pipes at some locations as the storm-sewer system is expected to accommodate a 100-year storm event even with reduced pipe sizes.
  • SWMO 11A-305: Rate control requirements, as the developer is requesting a rate reduction for on-site wetlands to meet Department of Environmental Protection requirements.
  • SALDO 13-512.1 and 13-512.2: Amount of required concrete monuments, as modern surveying technology does not require as many monuments as were once needed, with three planned for the development.
  • SALDO 13-515.9.G: Street tree spacing, as while the developer provides the amount of street trees required, some are spaced out more than 60 feet apart due to other requirements.
  • SALDO 13-510.7: Cartway width requirements, as the ordinance requires wider pavement widths for roads with on-street parking, but the plan does not include on-street parking and developers argue that widening roads beyond 30 feet would encourage speeding.
  • SALDO 13-510(B): Access drive widths, with the developer planning 22-foot two-lane access drives (with 8-foot parallel parking spaces) instead of 24-foot two-lane access drives as required by ordinance. The developer states that the extra parallel parking is not required by ordinance and can make access drives meet borough requirements by removing parallel parking. A fire department representative said the plan satisfied his earlier concerns about emergency services access.

Many of these waivers are regularly granted to developers, such as the pipe width, number of concrete monuments, and basin fencing requirements.

Conrad asked why the ordinance includes these requirements if they are so often waived. Borough engineer Jeff Steckbeck said the ordinance was designed to be strict, with opportunities for the borough to waive requirements when justifiable. He said the borough could always revisit its zoning ordinance.

Alongside the Granite Street improvements waiver, Cornwall Properties is also seeking a waiver for Silver Street improvements as there is no existing road.

The commission recommended approval contingent on council separately making a decision on the Granite Street waiver and the developer resolving outstanding comments (most administrative) from the engineer and solicitor. The commission also recommended allowing a retaining wall in the borough right-of-way under the condition it would be maintained by the Knoll homeowners association. Karinch abstained from all matters connected to the plan.

Cornwall residents have voiced opposition to the plan due to concerns about traffic on borough roadways, stormwater runoff and flooding (with multiple complaints associated with the Cornwall Properties’ Cliffs development), and other issues, including soil contents and worries about mine shaft locations.

The latter items were addressed by Steckbeck as borough engineer and zoning officer in a presentation Monday. (Steckbeck, who founded Steckbeck Engineering but has since retired, does not review plans linked to the firm like the Knoll plan but often provides context on the borough’s history and zoning protocols.)

Residents attend Monday’s planning commission meeting.

The development is allowed by right in the village residential district and meets borough zoning requirements outside of the items requested waived, according to Weaber’s review of the plan.

“Our job is to follow the ordinance the way it’s set before us; your battle now lies with the council,” Fratini told residents opposed to the plan. Shank responded that the commission was the one voting that night.

“We are an advisory board; what we are going to vote on is what’s before us with the laws that we must follow,” replied Fratini. “That’s what we’re gonna vote on, you understand that, you understand where I’m coming from? Whether you want to accept that, do you understand where I’m coming from?”

Fratini said he is “tired of being stepped on” and “of being accused of things that don’t exist” in reference to criticisms from residents about how their concerns are handled, as well as online claims that have been made about government officials.

Cornwall Borough Council is required to make a decision on the plan at its Oct. 12 meeting unless the developer grants another time extension, which Cornwall Properties has not indicated interest in doing.

The Knoll plan up for approval is one phase, with the western portion of the 74.114-acre site tentatively planned for more homes if a Miners Village bypass is constructed.

Conrad, who is leading negotiations with the Elizabethtown Area Water Authority (EAWA) to purchase land around Miners Lake for a bypass, said they plan to start meeting to discuss possible details of a sale soon. The borough has agreed to provide an escrow to EAWA to research possible environmental impacts of a sale and possible conditions to place upon a sale to ensure the quality of the lake’s water.

A graphic showing Miners Lake with the parcels the borough seeks to obtain in yellow. The parcels under discussion are to the right and left of the lake, at 0.93 and 1.75 acres, with potential bypasses (labeled A and B) also shown. The third parcel, totaling 3.33 acres, was sought by the borough for recreational purposes, but EAWA is not interested in selling. (LebTown file photo by Emily Bixler)

Conrad asked Swank if Cornwall Properties would be willing to wait to work on new plans for the rest of the Knoll site until EAWA discussions are completed and the borough knows whether it will construct a bypass. Swank said he was fine with that as long as council provided a reasonable timeline.


Cornwall P&Z meets the first Monday of each month at 6:30 p.m. and council meets the second Monday of each month at 6:30 p.m. Meetings are livestreamed.

Questions about this story? Suggestions for a future LebTown article? Reach our newsroom using this contact form and we’ll do our best to get back to you.

Join our community of local news champions.

Cancel anytime.

  • Still no paywall!
  • Fewer ads
  • Exclusive events and emails
  • All monthly benefits
  • Most popular option
  • Make a bigger impact

Already a member? Log in here to hide these messages

Trustworthy local news is built on facts. As Lebanon County’s independent news source, LebTown is committed to providing timely, accurate, fact-based coverage that matters to you. Support our mission with a monthly or annual membership, or make a one-time contribution. Cancel anytime.

Emily Bixler was born and raised in Lebanon and now reports on local government. In her free time, she enjoys playing piano and going for hikes.

Sound Off

What’s your take on this story?

Anyone can comment. Sign your name or post as a guest. Please keep it on topic and respectful.


★ MEMBERMembers’ comments are featured.