Cornwall Borough’s Planning & Zoning Commission heard a presentation from engineer and zoning officer Jeff Steckbeck addressing claims made by residents about soil testing, the history of mining in the area, and ethics allegations at a meeting Oct. 5.

Given the history of mining operations in Cornwall, residents have questioned whether areas slated for development, like the area around Miners Lake, could be at risk of cave-ins or dangerous chemicals in the soil.

However, submitted plans have not placed new development in identified areas unsafe for development due to mining, or subsidence areas, Steckbeck said. Steckbeck said a map of subsidence areas from Cornwall Mine #4 was prepared in 1992 by Charles Taylor Associates leading up to the development of Iron Valley Estates and the golf club.

“There were three lots that were affected … and the deeds for those properties were sold with the restriction that the property owners were not allowed to construct anything in the subsidence zone,” said Steckbeck of the Iron Valley Estates Phase 1 plan. “That plan was approved. Same thing occurred for Iron Valley Estates Phase 5A. That, I guess, would transfer over; the same subsidence limits would apply to current projects that have been under review such as the Cliffs and the Knoll.”

He showed a map of the area including mine shafts #4 and #5, which he explained collapsed between 1972 and 1999 and created “Cave Lake.”

Steckbeck explained that the Cornwall Ore Mines contained three shafts in the Miners Village and Open Pit areas, and showed the following graphics explaining their history (Steckbeck’s captions are added with minor formatting edits).

Concerning soil study concerns, Steckbeck said a study may have been conducted in 2006 while Haines & Kibblehouse was working toward constructing a rock crushing plant. He said he told the public in August that files may be available in the borough and the Department of Environmental Protection.

“We have no soil testing data in the files here in the borough, there was none provided to us, there may have been some provided to DEP in the issuance and approval of these permits,” said Steckbeck.

He requested that Dr. Jane Clark, who has opposed the Knoll and warehouse plans in part due to concerns about soil quality, rescind what he called “erroneous, baseless claims” of a cover-up she posted to Facebook. He gestured to two boxes of files set aside for interested residents including permits for air quality and rock transport, and he said Clark and other residents are welcome to review them.

“I’m gonna tell you, ladies and gentlemen, this is nonsense,” said Steckbeck. “It’s a lie, there was no cover-up, there was no information withheld. I provided knowledge of what I knew about the files and I made the files available. I request that Dr. Clark to retract this; the use of the word ‘cover-up’ represents nefarious conduct; nothing could be further from the truth.”

Steckbeck also referenced a presentation from resident Thora Hammersmith at council’s Sept. 14 meeting, which included resident-conducted water testing of runoff from the Cliffs development. Testing found the water to violate DEP standards due to a manganese makeup of 0.087 mg/L, above the 0.05 mg/L threshold, according to Hammersmith’s presentation.

A screenshot of testing provided in Thora Hammersmith’s presentation.

Steckbeck emphasized that the sample passed tests of every mineral except for manganese. He said state standards of 0.05 mg/L of manganese are due to potential staining and a metallic taste, but that it is safe to drink up to 0.3 mg/L. He also questioned whether the test was properly conducted.

A Pennsylvania Department of Health document (PDF) on manganese says that areas with a history of mining tend to have higher manganese levels in surface water. It categorizes the 0.05-0.1 mg/L range as “in most cases, not likely to pose a health risk” but notes “laundry or sink ware may experience cosmetic damage.”

Steckbeck said Hammersmith’s presentation was “a lot of bluster and bluff and should not be considered as being serious.”

He also said a resident alleged that Cliffs runoff flooded the Iron Furnace, and said this could not be true due to the topography of the area.

Steckbeck said he received his ethics review from the State Ethics Commission Monday for his work as zoning officer and code enforcement officer. Though he is still waiting on feedback from council and the borough solicitor, he said his opinion is that the review clears him to handle zoning and code enforcement complaints connected to his extended family, friends, past clients, or Steckbeck Engineering & Surveying Inc. (SESI).

“So they cleared me to do reviews of zoning and code matters of any clients of [SESI],” he said. He added that borough council still needs to make a determination about whether he should handle blasting permit requests from SESI and its clients.

Steckbeck founded SESI in 1990 and retired as SESI president in 2025. He still works as an engineer, including for Cornwall Borough, as independent contractor through Municipal & Authority Support Services LLC. However, plans connected to SESI are handled by alternate engineer Josh Weaber.

Residents have also alleged a conflict of interest by Weaber as he worked for SESI before founding Chrisland Engineering in 2017. A State Ethics Commission review of Chrisland Engineering found the firm was not considered a public official, though residents have complained that Weaber was not evaluated as an individual. Monday, Weaber said the review came back fine and he was not interested in discussing it further.

Also at Monday’s meeting, the commission:

  • Announced plans to discuss a proactive zoning review including gap analysis, geotechnical and soil analysis, elevation and topography comps, and changing elevation on a lot line, during a meeting Nov. 9 at 10:30 a.m. The commission will not hold a morning meeting this month.
  • Unanimously agreed to recommend the borough adopt a two-week submission deadline, which would require a developer to submit plans at least two weeks prior to a commission meeting to be evaluated during that meeting.
  • Heard a follow-up on the Cliffs at Iron Valley, including that a specialist plans to plant remaining required trees on site this season.
  • Approved a lot addition at 106 Lackawanna Drive, with commission member John Karinch abstaining, as it is his property.
  • Unanimously approved minutes.

The planning commission meets the first Monday of each month at 6:30 p.m. Meetings are open to the public and do not require prior registration.

Questions about this story? Suggestions for a future LebTown article? Reach our newsroom using this contact form and we’ll do our best to get back to you.

Join our community of local news champions.

Cancel anytime.

  • Still no paywall!
  • Fewer ads
  • Exclusive events and emails
  • All monthly benefits
  • Most popular option
  • Make a bigger impact

Already a member? Log in here to hide these messages

Quality local news takes time and resources. While LebTown is free to read, we rely on reader support to sustain our in-depth coverage of Lebanon County. Become a monthly or annual member to help us expand our reporting, or support our work with a one-time contribution. Cancel anytime.

Emily Bixler was born and raised in Lebanon and now reports on local government. In her free time, she enjoys playing piano and going for hikes.

Sound Off

What’s your take on this story?

Anyone can comment. Sign your name or post as a guest. Please keep it on topic and respectful.


★ MEMBERMembers’ comments are featured.