The Cornwall-Lebanon school board unanimously approved change orders for ongoing renovation projects during its regular meeting Monday.
For the high school project, the board approved a $6,186 change order from Jay R. Reynolds Inc. for various items and a $42,385.50 change order from Iron Eagle Excavating LLC to replace a fire hydrant, relocate the water service tap, and install additional rain leaders. The board also approved a $67,576.09 change order for various items from general contractor Lobar Inc.
For the stadium improvements project, the board approved a $36,853.63 change order from NCI Construction Ltd. including a $43,028.63 pump station replacement and a $6,175 credit.
The high school renovation, which is expected to be completed in April or May of 2028, includes 8,306-, 2,254-, and 2,116-square-foot additions and remodels of existing spaces.
The stadium renovation, largely completed, includes the construction of a large concession stand and restroom facilities, as well as lighting/sound, bleachers, and ADA improvements. Contractors are still finalizing punchlists, district construction manager Fidevia’s September report on the stadium says.
Read More:
Fidevia’s September high school renovations report says remodels of the cafeteria, kitchen, and serving area are complete and in use. A new coffee shop has been completed, the report says, and new Hydro Labs are 90% complete. The report also describes progress on utilities, demolition, and other remodels.
High school renovations were originally bid for $91,508,600 total and $167,855.67 in change orders were approved as of the September report. The report for the stadium lists approved change orders for the $10,177,544-bid project as totaling $239,404. Neither of these reports include change orders approved Monday.
The board unanimously approved the payment of campus renovation bills totaling $4,021,291.32 Monday. It also unanimously approved a transfer of $8 million from the general fund to the campus project fund.
Board members also unanimously approved a $1.5 million transfer from the general fund into the healthcare fund. During its Oct. 12 work session, the board heard that the 2025-26 school year saw a 32% increase in self-funded program costs.

The fund ended the year with a negative variance of $1.74 million, according to the presentation, and the district plans to use programs like Rx ‘n Go Prescription and Penn Medicine HealthWorks Centers to bring down costs in the future.
Read More: (October 2026) CLSD board preps for possible Lebanon withdrawal from CTC
During Monday’s meeting, Susan Dieffenbach addressed federal funding of the Head Start program during her report on the 22-member Intermediate Unit 13 board, of which she is treasurer and Cornwall-Lebanon representative. Last year, she said, the federal government was considering cuts to the program that were eventually cancelled.
“There was bipartisan pushback against the moves and so that was squashed,” she said. “The success of the Head Start programs, early intervention programs, is absolutely unquantifiable, so we can’t just measure it in dollars. Right now, there’s a move to make another cut to the Head Start administration to put caps on how much can be spent on administration of Head Start funding, which is absurd.”
The program provides eligible parents with home visits and provides information on child development and health and community services, the IU13 website reports.
In other news, the board:
- Unanimously approved the payment of $11,464.15 in capital reserve fund bills.
- Unanimously approved the final adoption of the district’s virtual attendance and wellness checks, bullying/cyberbullying, and local taxpayer bill of rights policies.
- Unanimously approved credit reimbursements totaling $29,493.81.
- Unanimously ratified the 2026-27 contract with Maxim Healthcare and food service fund bills totaling $471,398.81.
- Unanimously approved Brightbill Transportation bus drivers.
- Unanimously approved various extracurricular requests.
- Unanimously approved various personnel items.
- Heard reports and unanimously approved minutes.
- Honored National Merit commended students Annika Rosenberg and Asha Patel for high Practice SAT scores.
- Honored October Students of the Month Tobias Felker and Iyanna Obuobisa.
- Heard an update from high school Student Council representatives Sage Henery and Molly MaCauley.
This meeting was covered remotely by LebTown using a livestream of the meeting posted to the district’s YouTube page and notes from previous coverage of the board.
The Cornwall-Lebanon school board holds a work session on the second Monday and a regular meeting on the third Monday of each month, both at 5:30 p.m. Meetings are held at South Lebanon Elementary School due to ongoing construction at Cedar Crest High School.
Questions about this story? Suggestions for a future LebTown article? Reach our newsroom using this contact form and we’ll do our best to get back to you.

Join our community of local news champions.
Cancel anytime.
Monthly
🌟 Annual
- Still no paywall!
- Fewer ads
- Exclusive events and emails
- All monthly benefits
- Most popular option
- Make a bigger impact
Already a member? Log in here to hide these messages
Strong communities need someone keeping an eye on local institutions. LebTown holds leaders accountable, reports on decisions affecting your taxes and schools, and ensures transparency at every level. Support this work with a monthly or annual membership, or make a one-time contribution. Cancel anytime.