This article was funded by LebTown donors as part of our Civic Impact Reporting Project.
The Bethel Township Planning Commission is recommending that supervisors approve the Cook Facility plan with a Bell & Evans request to allow a $350,000 payment to the township if plans for a walking path fall through.
The commission unanimously recommended that township supervisors agree to give Bell & Evans the option of a $350,000 fee in lieu of for the facility, which it could declare three months prior to occupancy. Bell & Evans chief operating officer Mike Bracrella said the developer still intends to come to an agreement with the Fredericksburg American Legion Post 915 to obtain a right-of-way and complete the planned walking path.
Bracrella said the Legion has been “very cooperative” and is “not opposed” to the agreement, but there have been delays as Legion representatives confer with their lawyer.
Construction of a full pathway was part of the agreement for the poultry producer to build the Cook Facility on the south side of Route 22 near Fredericksburg Road. Bell & Evans, Bracrella explained, still wants to complete the path, but would like to be able to start construction as soon as possible.
Multiple commissioners said their hope was for the right-of-way to be obtained and the full path constructed, which Bracrella said was also his goal. Though Bracrella suggested a six-month from occupancy deadline, the commission opted to suggest a three-month from occupancy deadline so Bell & Evans would not need to seek a time extension if the agreement moved slowly.

Though sketches for the path have shown it going down Route 22 to its intersection with Legionaire Drive, Bracrella said he would be willing to wind the path down Elizabeth Run and over the car bridge behind the Legion if the Legion has problems with the proposed location. This would still require right-of-way approval.

The motion recommended a general fee in lieu of, which would not require funds to go specifically toward new sidewalks. The township would not be able to construct the same path with $350,000, commissioner Bruce Light said, especially as it would also need to acquire a right-of-way agreement with the Legion.
The path is planned as an offsite improvement for the 120,000-square-foot Cook Facility, with the ability to add 65,000 square feet in a future expansion. The ready-to-eat meal manufacturer includes plans for team member and tractor-trailer parking with separate entrances off Fredericksburg Road and five stormwater drainage facilities, Bethel solicitor Andrew Morrow said during the supervisors’ Oct. 8 meeting.
If the walking path is constructed, Bell & Evans would be responsible for its maintenance. Bracrella said Bell & Evans’ goal is to create a loop spanning Route 22 and Fredericksburg, Chestnut Hill, and Blue Mountain roads. However, the path will be built in portions as Bell & Evans works through multiple developments planned for the area.

Supervisors will have the option to accept or reject the planning commission’s suggestion at their Nov. 12 meeting.
The commission also discussed requested waivers from Bell & Evans for highway improvements at Blue Mountain and Chestnut Hill roads.

For intersection improvements, Bell & Evans engineer Alex Kinzey said the developer’s initial plan was to realign the western side of Chestnut Hill Road to meet Blue Mountain Road at around a right angle, but that would require obtaining permission from a Chestnut Hill Road property owner to grade into their embankment. However, he said, they could not work out an agreement.

Kinzey also presented an updated plan with a sharper angle, which would not require an agreement with the neighboring property.

Commissioners said they would prefer the first plan because of safety concerns. Commissioners ultimately asked Bell & Evans to try to draft a plan with a right-angle intersection and an S-curve on Chestnut Hill Road leading up to the intersection.
The developer requested a waiver of section 23 of the stormwater ordinance for total runoff on Blue Mountain Road, which the developer is widening and adding curbing and sidewalks. Bell & Evans engineer Alex Kinzey explained that the drafted improvements would increase runoff but redirect it onto Bell & Evans property to the east of the road.
He said the developer could decrease runoff to township standards, but doing so would direct some stormwater toward three adjacent homes because of the road’s center line moving. He said existing stormwater management is ineffective, with storm pipes that are clogged and a homeowner’s stormwater channel in need of cleaning. Bracrella later said he would reach out to the property owner to ask for permission to restore it.
The planning commission suggested raising the road using box culverts, but Bracrella said that could end up being a temporary fix depending on the future of Bell & Evans’ now-empty lot across from the homes.
No action was taken on road improvements Tuesday, but Bracrella said Bell & Evans would return with a plan for the commission to review by its Nov. 17 meeting.
In other news, the commission:
- Unanimously agreed to send a drafted amendment to the stormwater ordinance to supervisors, which sets the agricultural exemption max at 20,000 square feet and defines semi-impervious surfaces.
- Unanimously agreed to take a position against the township placing “local delivery only” signs on the east side of Chestnut Hill Road, noting that Bell & Evans traffic is local and the township could not enforce the rule without a police department.
- Unanimously accepted the Travis Berger Ag Operation plan for review.
- Unanimously recommended the acceptance of a time extension until Feb. 15 for the Earlakill Farms plan.
The next meeting of Bethel Township supervisors is Thursday, Nov. 12, at 7 p.m. in the township building at 3015 S. Pine Grove St., Fredericksburg. The commission will meet the following Tuesday, Nov. 17.
Questions about this story? Suggestions for a future LebTown article? Reach our newsroom using this contact form and we’ll do our best to get back to you.

Join our community of local news champions.
Cancel anytime.
Monthly
🌟 Annual
- Still no paywall!
- Fewer ads
- Exclusive events and emails
- All monthly benefits
- Most popular option
- Make a bigger impact
Already a member? Log in here to hide these messages
Local news is a public good—like roads, parks, or schools, it benefits everyone. LebTown keeps Lebanon County informed, connected, and ready to participate. Support this community resource with a monthly or annual membership, or make a one-time contribution. Cancel anytime.