This article was funded by LebTown donors as part of our Civic Impact Reporting Project.

Due to rising costs, a Heidelberg Township trailhead and walking path project initially expected to cost $170,000 will cost $256,966.55, even with cuts to project scope.

Heidelberg supervisors unanimously agreed to approve an updated scope of work and higher cost for the partially grant-funded project at their monthly meeting Tuesday.

The project, including a trailhead at the 0.4-acre parcel acquired by the township last year, an extension of the trail, and resurfacing of the existing trail and baseball and softball fields, was originally expected to cost $170,000, to be split between a $100,000 Pennsylvania Department of Conservation and Natural Resources (DCNR) grant and a $70,000 match from the township. However, township engineer Nick Ebersole explained, rising costs over the last year and a half led to significant increases in the expected cost.

Ebersole said he worked with the park and recreation board to lower costs, including by doing some prep portions in-house, reducing total length and width of the new path, and by choosing a lower-priced option for a trailhead sign. Even with these scope revisions, he said, the project is still slated to cost $86,966.55 more than expected.

Ebersole said he was hesitant to make further cuts to the plan due to the DCNR funding. He said he had encountered cases in other municipalities where plan scopes were significantly cut due to higher costs and, as a result, DCNR was less willing to work with those municipalities in the future.

“When you get [DCNR grant funding], it’s kind of an honorable thing and you wanna keep that, so to reduce the park down to a level they may not have awarded the grant in the original place is what you’re trying to avoid,” said Ebersole. “You also want to keep those relationships for as you move ahead.”

Township manager Jen Snyder said the draft 2027 budget includes the additional cost and would not need to be revised. Supervisors Paul Fetter and Steve Martin (with Ivan Martin away on vacation) agreed to approve the change of scope and cost, subject to final budget approval.

The draft budget, which supervisors plan to advertise for a public hearing at their Nov. 17 meeting, does not include a tax increase. Supervisors held meetings to look over the budget Oct. 7 and 14.

In other news, supervisors:

  • Unanimously approved a payment of $12,373.54 to plumbing contractor Fox & Long for the township building interior remodel. Solicitor Paul Bametzreider said he made a demand on the bond issued by a previously hired contractor that did not complete the contract.
  • Unanimously agreed to direct Bametzreider to draft an ordinance establishing a procedure for residents to request and be issued handicap parking spaces, which would allow the township to approve future requests via resolution.
  • Unanimously approved an addendum to an escrow with the Copper Ridge development extending provisions into future phases of the plan.
  • Heard that a newly drafted data center ordinance has been sent to the planning commission and county planning.
  • Unanimously agreed to transfer pension funds provided by the state from the general fund to the pension fund, as well as the township’s minimum municipal obligation not covered by the state.
  • Unanimously approved minor electric installation work for the township building expected to cost $1,850 and the purchase of a $1,244.85 racking system.
  • Unanimously approved the purchase of a $1,799 storage system for the public works shop.
  • Unanimously approved the purchase of two 6- by 10-foot steel plates for public works to allow them to safely close one lane of traffic.
  • Directed Bametzreider to send a letter to a property owner that they will be be held responsible for logging damage to a township road and will be expected to pay back repair costs totaling $6,943.
  • Unanimously approved the part-time hire of a resident to do snow plowing, to work as-needed depending on winter weather.
  • Unanimously approved the sale of a 1999 grader on Municibid, subject to final board approval.
  • Unanimously agreed to acknowledge an Agricultural Security Area application from the Glenn Zimmerman farm.
  • Unanimously approved a request for the fire police to assist at a trick-or-treat event and a holiday event Nov. 22.
  • Unanimously agreed to submit a permit application for a new well to the Department of Environmental Protection and approve a sewer planning module exemption for the well.
  • Unanimously approved the purchase of a blower for Flintville Pump Station for around $1,800.
  • Unanimously approved a $1,000 quote for foliage trimming at the pump station.
  • Unanimously authorized Snyder to advertise for a part-time administrative position.
  • Unanimously approved minutes and bills and heard reports.

Heidelberg Township supervisors will next meet Nov. 17 at 6:30 p.m. These meetings are open to the public and do not require prior registration.

Questions about this story? Suggestions for a future LebTown article? Reach our newsroom using this contact form and we’ll do our best to get back to you.

Be part of Lebanon County’s story.

Cancel anytime.

  • Still no paywall!
  • Fewer ads
  • Exclusive events and emails
  • All monthly benefits
  • Most popular option
  • Make a bigger impact

Already a member? Log in here to hide these messages

You know us because we live here too. LebTown’s credibility comes from showing up, listening, and reporting on Lebanon County with care and accuracy. Support your neighbors in the newsroom with a monthly or annual membership, or make a one-time contribution. Cancel anytime.

Emily Bixler was born and raised in Lebanon and now reports on local government. In her free time, she enjoys playing piano and going for hikes.

Sound Off

What’s your take on this story?

Anyone can comment. Sign your name or post as a guest. Please keep it on topic and respectful.


★ MEMBERMembers’ comments are featured.